Building a pump station screen from a symbol library: symbols, pipes and a test run

Reservoir, two pumps and a tower: which symbols a pump station screen needs, how pipes should show flow, and how I test a screen before operators rely on it.

A pump station screen built from a symbol library shows the station as it is piped: the source the pumps draw from, each pump and its state, the discharge valves and instruments, and where the water goes. Place symbols in flow order, draw pipes in the direction water moves, and test every state before go-live.

Hermetry 2.0, released on 26 August 2026, brought SCADA process screens drawn in 2D and 3D from a symbol library (see the SCADA process drawings documentation). This guide covers the drawing for a small 2D station: a ground reservoir, two pumps and the tower they fill. Where the screen sits among the others is in my post on HMI display hierarchy.

Which symbols does a pump station screen need?

It needs one symbol for every part an operator would name on the phone, and nothing decorative. I start from the station’s P&ID, which already lists the equipment and instruments (see how to read a P&ID).

  1. The source: the reservoir or wet well, drawn as a vessel that shows its level.
  2. Each pump as its own symbol.
  3. The check valve and the isolation valve on each pump’s discharge. The check valve is what stops water flowing back through a pump that has stopped.
  4. The instruments on the common discharge: a pressure transmitter and a flow meter.
  5. The destination, here the tower, with its level.

Drains, vents and spare flanges stay on the P&ID.

How do pipes show flow on a SCADA screen?

A pipe should show flow only when a signal says water is moving: the pump at its upstream end is running, or the flow meter reads above zero. A pipe that always animates tells the operator nothing.

Draw every pipe from upstream to downstream. If your tool ties a pipe’s state to one of the symbols at its ends, check which end it uses, because a discharge pipe drawn backwards can end up following the tower instead of the pump.

Keep the pipe quiet while water flows normally. Colour is for the abnormal, as Sema explains in why most of an operator screen should be grey.

How do you set up what each symbol shows?

Each symbol should show the one or two things an operator acts on, in the units they think in: level in metres or percent for the reservoir and the tower, run state and fault for each pump.

  • Scale levels once, before the value reaches the screen; a level drawn against the wrong range can look half full when the tank is nearly empty. Measuring the level is covered in water tank level monitoring.
  • Name symbols the way the field does. If the panel says Pump 1, the screen says Pump 1.
  • Draw identical pumps identically: same symbol, same size, label in the same place.

How do you test a SCADA screen before going live?

Test in two passes: first with simulated values, then against the real signals one at a time.

  1. Simulate each state of each symbol (running, stopped, fault, level low, level high) and check that pipes and colours change as you expect.
  2. With the station connected, have someone on site change one signal, such as starting a pump locally, and confirm that the right symbol changes. Repeat for every signal.
  3. Sit an operator in front of the screen and ask which pump is running, whether the tower is filling and whether anything is wrong. If they have to ask you, the screen is not finished.

The screen supervises; it does not replace the station’s own protection, such as low-level and dry-run trips in the panel.

Frequently asked questions

Should a pump station screen be 2D or 3D?

Draw the 2D screen first, because operators work from it: every pump, valve and level reads at a glance. A 3D view helps people who do not know the station, such as a new technician. Hermetry 2.0 draws process screens from its symbol library in both 2D and 3D.

How many pumps fit on one station screen?

As many as the station has, while each pump still reads clearly without scrolling. When a station outgrows one screen, I split it by area, such as intake and booster pumps, under a station overview that leads to each one.

Should operators start pumps from the screen?

The site decides that, not the drawing. If remote commands are allowed, I put them on the pump’s detail view rather than the overview, with a confirmation and a record of who sent each one. Local controls and protection must keep working whatever the screen does.