How to read a P&ID: instrument tags, bubbles and line symbols

A reading order for piping and instrumentation diagrams: legend and notes first, then process lines, then each instrument tag, its bubble and its signal lines.

To read a piping and instrumentation diagram (P&ID), start at the legend and notes, follow the process lines from equipment to equipment, then decode each instrument bubble. The letters of the tag say what is measured and what the instrument does, the number ties it to its loop, and the line through the bubble says where it is mounted.

Most of my work is screens for water and wastewater sites and process plants, and the good ones start from a P&ID. This is my reading order.

What standard do P&ID instrument symbols follow?

The usual reference for instrument tags and bubbles is ANSI/ISA-5.1 from the International Society of Automation. Its current edition is ANSI/ISA-5.1-2024, Instrumentation and Control – Symbols and Identification, and ISA says it covers the instrumentation and control content of drawings such as process flow diagrams and P&IDs.

Companies often use different or additional symbols, so I first read the drawing’s notes and legend, which list the special symbols and conventions it uses. When the drawing and my memory of the standard disagree, the legend wins.

What do the letters in an instrument tag mean?

The first letter names the measured variable, and the letters after it name what the instrument does with it. The number is the loop number, shared by every instrument in the loop.

PositionLetterMeaning
FirstF, L, P, TFlow, level, pressure, temperature
FollowingEPrimary element (the sensor)
FollowingTTransmitter
FollowingIIndicator
FollowingCController
FollowingVValve

A flow loop then reads as FT-101 (flow transmitter), FIC-101 (flow indicating controller) and FV-101 (the flow control valve). Position decides meaning: in TIC the T is temperature, in FT a transmitter. Some drawings write the valve as FCV-101, with C for control.

What is the difference between TE and TI on a P&ID?

TE is a temperature element, the sensor in the process. TI is a temperature indicator, where a person reads the value, on a local gauge or a control room display.

A common chain is TE-301 wired to TT-301, with TI-301 on the control system. On a screen the indicator becomes the number; the element and transmitter tell me where to look when it seems wrong.

What do the circles and lines on instrument bubbles mean?

The bubble says where the instrument lives. A plain circle is mounted in the field. A solid line across the circle puts it in a primary location the operator normally reaches, such as the control room panel. A double line marks an auxiliary location the operator can also reach, and a dashed line an inaccessible one, for example behind a panel.

Hermetry connects field devices to live dashboards, rules and alerts: IoT telemetry and SCADA in one platform. Its Process library, one of 13 industry libraries sold one by one, has an Instruments (ISA) family of 21 symbols, among them flow, pressure, temperature, level and analyser transmitters (FT, PT, TT, LT, AT) and indicating controllers (PIC, TIC, FIC, LIC).

What do the line types on a P&ID mean?

Process piping is drawn heavier than instrument lines, and a thin line’s pattern gives the signal type. In the convention most process engineering courses teach:

  • a line with short double slashes is a pneumatic signal;
  • a dashed or dotted line is an electric signal;
  • software signals have a line symbol of their own.

Not every drawing follows it (one university course marks electric lines with E’s and pneumatic lines with A’s), so check the legend. The glossary of IoT and SCADA terms helps when the drawing becomes a screen.

How is a P&ID different from a block flow diagram?

A block flow diagram shows the process units as blocks joined by the streams between them. A process flow diagram shows the major equipment, each with its own number, and the process and utility streams. A P&ID builds on the PFD with valves, piping details, instruments and control loops.

For a pump station monitoring screen, or for checking a loop in the field, the P&ID is the drawing I keep open.

Frequently asked questions

Is a P&ID drawn to scale?

No. As a rule a P&ID has no drawing scale and shows only how components connect and in which order. Two pieces of equipment drawn side by side need not even be in the same building, and most pipe routing details are left out.

What does a square around an instrument bubble mean?

It marks a shared display and shared control function, one that lives in a digital control system. A process control textbook appendix says the square means the function is implemented via digital control. A hexagon marks a computer function instead.

What should I do with a symbol I cannot find in the standard?

Check the drawing’s notes and legend, which list the special symbols and conventions used on it. If neither explains the symbol, ask whoever owns the drawings; a guessed symbol copied onto an operator screen spreads the mistake.