This OEE calculator multiplies availability × performance × quality. 420 planned minutes with 47 down, a 1-second ideal cycle and 18,848 good of 19,271 parts give 88.8 % × 86.1 % × 97.8 % = 74.8 % OEE.
- OEE
- –
- Availability
- –
- Performance
- –
- Quality
- –
- Run time
- – min
- Fully productive time
- – min
Performance is above 100 %: the ideal cycle time is probably set too long.
Enter a planned time above zero, a downtime shorter than it, an ideal cycle time above zero, and good parts no more than parts made.
How it works
How is OEE calculated?
Availability is run time ÷ planned production time, where run time is the planned time minus downtime.
Performance is ideal cycle time × parts made ÷ run time: how close the machine ran to its fastest. Quality is good parts ÷ parts made.
OEE is availability × performance × quality. It also equals the fully productive time (good parts × ideal cycle time) ÷ planned production time.
In Hermetry Hermetry collects the machine states and the good and reject counters OEE is built from: Production tracking with machine counters.
Glossary OEE (overall equipment effectiveness), Availability, MES (manufacturing execution system)
Questions
Questions about the OEE calculator
What are the three OEE factors?
Availability (losses from stops), performance (losses from running slower than the ideal cycle) and quality (losses from bad parts). OEE multiplies them.
Why can performance come out above 100 %?
The ideal cycle time is set longer than the machine really needs. Use the fastest cycle the machine can run, not a planning figure.