This load factor calculator divides the average load by the peak demand: 360,000 kWh over a 720-hour month is 500 kW on average, a 62.5 % load factor against an 800 kW peak.
- Load factor
- – %
- Average load
- – kW
- Equivalent full-load hours
- – h
Above 100 %: the peak is lower than the average, so one of the inputs is off.
Enter energy of 0 or more and hours and a peak above zero.
How it works
How is load factor calculated?
Average load = energy ÷ hours in the period. Load factor = average load ÷ peak demand.
A load factor near 100 % means a flat, steady load; a low one means short peaks well above the usual load, the kind demand charges punish.
Equivalent full-load hours = energy ÷ peak: the hours the site would need at its peak to use the same energy.
In Hermetry Hermetry works out load factor as average load ÷ peak load over a month for each transformer: Substation and transformer monitoring.
Glossary Demand charge, Peak shaving, Load profile
Questions
Questions about the load factor calculator
What is a good load factor?
It depends on the site: continuous process plants run high, offices and schools low. Track it over time; a falling value means peaks are growing faster than use.
How do I raise the load factor?
Shift flexible loads such as charging, pumping and cooling out of peak hours, stagger motor starts, and cap peaks with storage or load shedding.